School Expansion

Kent County Council have asked Trinity School to expand from 4fe (120 students per year) to 6fe (180 students per year). To accommodate this, the school building will be extended, with work starting in phases from September 2018. As well as additional classrooms, this work will also add additional dining facilities, increase the size of the Sixth Form centre, and include a dedicated drama studio, a second indoor PE space, and more outdoor play space.

Phase 1 was completed successfully in July and August 2018 with the addition of 6 classrooms, and a mezzanine floor in the dining room.

You can find a link to copies of drawings below. Please note these are currently in draft, so should be used as a rough guide only. Once the final drawings are confirmed we will add further updates here.

Trinity School Expansion Proposed Drawings